Plan Review Comments Plan Review Comments Search
Plan Review Results:
This is an incomplete listing of your review for this project.  Do not bring any revisions pertaining to this review.  If revisions will be required, a complete listing of review comments will be faxed or emailed to the project contact person upon the completion of this review cycle.
 
NOTE:
Once all review trades are approved and there are no outstanding administrative issues such as map recordings, contractor licensing information, etc., it could take up to three (3) days before your project will be ready for permit pick-up. Your project contact person will be notified via fax, email or phone.
  Transaction Number:     379618   Contact Person:   CLEMMONS, SHAWN
          Phone:   (919) 835-1500
          Fax:  
  Review Type Description:   Also had a CTR on 11/14/13 T-373565 12 story, I-A, 576000sf bldg w/260,000sf to be reviewed. Addition of 12 story office tower on existing 315000sf reinforced concrete underground parking structure. Construction of structural system, exterior envelope..interior lobby completion
  Plan Address:   501 FAYETTEVILLE ST
  Group Created:   12/19/2013   Started Plans Routing:   10/30/2013   Review Approved:   02/28/2014
  Final Review Approved:   03/14/2014   Permits Issued:   03/14/2014        
 
Review Cycle - 2 Started - 02/28/2014 Completed - 02/28/2014
Trade Status Reviewer Date
TRANSPORTATION CONDITIONALLY APPROVED BRADLEY KIMBRELL
(919) 996-6810
02/28/2014
1 Approval is given with the condition that the overhead pedestrian protection structure, used in conjunction with the sidewalk closure, be approved by City staff and a separate tunnel permit is issued..
2 Approval is given with the condition that Street and Sidewalk closures/restrictions follow the construction details approved by Council and the plans approved by Bradley Kimbrell..
3 The City Inspector has the authority to make changes to the traffic control plan as necessary in the field..
 
Review Cycle - 1 Started - 10/30/2013 Completed - 12/06/2013
Trade Status Reviewer Date
BUILDING APPROVED KENT DAVIS
(919) 996-2581
12/05/2013
1 This project can not be approved at this time due to unresolved issue with sidewalk and street closures for staging area and public pedestrian movement..
STORMWATER APPROVED SUSAN LOCKLEAR
(919) 996-3516
12/02/2013
1 No increase in impervious..
ELECTRICAL APPROVED RON KELLY
(919) 996-2621
12/06/2013
FIRE ALARM CONDITIONALLY APPROVED HARRY LOVIC
(919) 996-2181
12/06/2013
1 Fire Alarm Shop Drawings Required per 907.1.2.
2 No Fire Alarm Construction is Permitted..
3 Pending Construction Document Approval..
4 .
FIRE PROTECTION CONDITIONALLY APPROVED HARRY LOVIC
(919) 996-2181
12/06/2013
1 1st floor outside canopy or awning sprinkler protection is dependent upon the occupancy of the space.Sprinklers omitted under the shell building permit may be required when the interior completion plans are reviewed..
2 Shop drawing submittal is required for review of diesel fuel tank, piping, overfill protection, venting, emergency venting, etc....
3 ***DO NOT FILL DIESEL TANK PRIOR TO REQUIRED TANK PRESSURE TEST ON SITE***.
4 All fire hydrants, fire department connections, existing fire pump rooms, and parking deck egress must remain un-obstructed at all times..
5 FIRE SAFETY DURING CONSTRUCTION, NCFPC Ch.14 is required at all times during construction project.Temporary standpipe plan is required at time of 1st construction meeting..
SITE ACCESSIBILITY CONDITIONALLY APPROVED THOMAS BAIRD
(919) 996-2187
12/06/2013
1 Pending City Council approval of sidewalk/street closure.
ADDRESSING TEAM APPROVED WAYNE BREWER
12/05/2013
MECHANICAL APPROVED WILLIAM PRICE
(919) 996-2190
12/06/2013
TRANSIT APPROVED CARMALEE SCARPITTI
(919) 996-2291
12/05/2013
1 No transit comments.
CSC PLAN INTAKE PROC CONDITIONALLY APPROVED CELIA MCCOY
(919) 996-2571
11/25/2013
PUBLIC UTILITIES CONDITIONALLY APPROVED BRIAN CASEY
12/05/2013
1 Pending City Council approval of lane closures..
2 any unused W/S services to be abandoned per PU Handbook..
3 BFP's in building.2- fire lines.Fire line on Wilmington moved North for RFD..
PLANNING CONDITIONALLY APPROVED ERIC HODGE
(919) 996-2639
12/05/2013
1 Prior to C/O plans to be revised to include planters along Lenoir St.as previously shown..
2 Prior to C/O either get a revised encroachment to allow doors to swing out into Lenoir St.R/W or revise plans accordingly..
3 Prior to C/O project will need to meet all considerations of the UDA and that document must be signed prior to permits being picked up..
SOLID WASTE SERVICES CONDITIONALLY APPROVED ERVIN PETE
(919) 996-6919
12/05/2013
1 Project manager will send letter to SWS to show how private company will collect..
2 Ervin Pete 919-996-6919.
PLUMBING APPROVED WILLIAM PRICE
(919) 996-2190
12/06/2013
TRANSPORTATION UNRESOLVED BRADLEY KIMBRELL
(919) 996-6810
12/05/2013
1 Three items are still unresolved with this project..
2 The Sidewalk and Lane Closure/Restrictions shall be worked out with Construction Management and Transportation Operations.However, a conditional approval could be given for this item once all other issues have been addressed..
3 The Security bond shall be posted with the City for the amount of 1.5 times the total estimate cost of public improvments.Coordinate with Bradley Kimbrell to review..
4 Construction drawings for the proposed ramping of the sidewalk along Fayetteville Street shall be finalized and approved by Transportation and Site Accessibilty prior to building permit issuance..
 
 